Installation of a scum collector and sludge thickener system

Québec, Quebec

completeWastewaterCWWF
Federal contribution
$403,454
Federal share50%

of $806.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2018
2018
Built

Approved 12 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Québec
Construction start
Jan 25, 2017(actual)
Construction end
Dec 1, 2017(actual)

Against the original forecast

  • Construction end16 months earlyforecast Mar 31, 2019

Also in Québec

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48840 in the federal list. How to read these figures.