Renewal of water pipes
Salaberry-de-Valleyfield, Quebec
Federal contribution
$1.0M
$1,045,454
Federal share50%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 24, 2017
2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Salaberry-de-Valleyfield
- Construction start
- Apr 28, 2016(actual)
- Construction end
- Jul 21, 2017(actual)
Against the original forecast
- Construction end8 months earlyforecast Mar 31, 2018
Also in Salaberry-de-Valleyfield
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48850 in the federal list. How to read these figures.