Water Systems Upgrades

Lévis, Quebec

completeDrinking WaterCWWF
Federal contribution
$3.4M
$3,449,614
Federal share50%

of $6.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
20172018
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Lévis
Construction start
Jul 27, 2016(actual)
Construction end
Jun 1, 2018(actual)

Against the original forecast

  • Construction start9 months earlyforecast May 1, 2017
  • Construction end10 months earlyforecast Mar 31, 2019