Renovation of U396, U397, U392 pumping stations and the addition of pumped overflow to the U303 pumping station

Québec, Quebec

completeWastewaterCWWF
Federal contribution
$856,828
Federal share50%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Québec
Construction start
Sep 1, 2017(actual)
Construction end
Oct 16, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 30, 2017
  • Construction end5 months earlyforecast Mar 31, 2019

Also in Québec

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48876 in the federal list. How to read these figures.