Redesign of step-level pressure controls in the Loretteville and St-Émile sector

Québec, Quebec

completeDrinking WaterCWWF
Federal contribution
$763,651
Federal share50%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2017
2017201920212023
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Québec
Construction start
May 18, 2018(actual)
Construction end
Mar 31, 2023(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Jun 4, 2018
  • Construction end9 months lateforecast Jun 30, 2022

Also in Québec

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48884 in the federal list. How to read these figures.