Repair and Rehabilitation of Pump Stations and Booster Station

Vaughan, Ontario

completeWastewaterCWWF
Federal contribution
$284,656
Federal share50%

of $569.3K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 28, 2017
ApprovedMar 27, 2018
201820192020
Built

Approved 8 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Vaughan
Construction start
Sep 30, 2017(actual)
Construction end
Sep 18, 2020(actual)

Against the original forecast

  • Construction start2 months earlyforecast Dec 1, 2017
  • Construction end12 months earlyforecast Sep 30, 2021

Also in Vaughan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49040 in the federal list. How to read these figures.