Rehabilitation of Four Stormwater Ponds to Restore Design Volumes and Efficiencies
Federal contribution
$571,300
Federal share44%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 28, 2017
ApprovedMar 20, 2018
20182019
Built
Approved 8 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Vaughan
- Construction start
- Nov 30, 2017(actual)
- Construction end
- Oct 2, 2019(actual)
Against the original forecast
- Construction start8 months lateforecast Apr 1, 2017
- Construction end3 months lateforecast Jun 30, 2019
Also in Vaughan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49047 in the federal list. How to read these figures.