Back to projects

Rehabilitation of Four Stormwater Ponds to Restore Design Volumes and Efficiencies

Vaughan, Ontario

completeWastewaterCWWF
Federal contribution
$571,300
Federal share44%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 28, 2017
ApprovedMar 20, 2018
20182019
Built

Approved 8 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Vaughan
Construction start
Nov 30, 2017(actual)
Construction end
Oct 2, 2019(actual)

Against the original forecast

  • Construction start8 months lateforecast Apr 1, 2017
  • Construction end3 months lateforecast Jun 30, 2019

Also in Vaughan