Church Street Stormwater pumping station pump improvements

Vaughan, Ontario

completeWastewaterCWWF
Federal contribution
$23,658
Federal share47%

of $50.2K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 28, 2017
ApprovedMar 27, 2018
20182019
Built

Approved 8 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Vaughan
Construction start
Oct 31, 2017(actual)
Construction end
Dec 31, 2018(actual)

Against the original forecast

  • Construction start7 weeks earlyforecast Dec 22, 2017
  • Construction end4 weeks earlyforecast Jan 31, 2019

Also in Vaughan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49055 in the federal list. How to read these figures.