Extension of the Water Supply System to Residences
Federal contribution
$89,999
Federal share50%
of $180.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
Built
Approved 8 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Saint-Prosper
- Construction start
- Oct 1, 2017(actual)
- Construction end
- Nov 30, 2017(actual)
Against the original forecast
- Construction start5 months lateforecast May 15, 2017
- Construction end16 months earlyforecast Mar 31, 2019
Also in Saint-Prosper
- Water treatment and distribution work$4.2M
- Construction of a multipurpose complex (arena and community hall) in Saint-Prosper$3.0M
- Program for the renewal of drinking water and wastewater pipes$1.7M
- Water and sewer pipeline for the 12th, 13th and 14th streets and 25th Avenue$446.9K
- Program for the renewal of drinking water and wastewater pipes$183.7K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49058 in the federal list. How to read these figures.