Retaining Wall Rehabilitation for Stormwater Management at Intersite Place
Federal contribution
$143,525
Federal share48%
of $300.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 24, 2017
ApprovedMar 27, 2018
201820192020
Built
Approved 10 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Vaughan
- Construction start
- Apr 1, 2017(actual)
- Construction end
- Dec 31, 2019(actual)
Also in Vaughan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49061 in the federal list. How to read these figures.