Investigation and design for the Replacement/Rehabilitation of sanitary sewer on Rivermede Road and Rayatte Road
Federal contribution
$47,500
Federal share50%
of $95.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 28, 2017
ApprovedMar 27, 2018
201820192020
Built
Approved 8 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Vaughan
- Construction start
- Nov 15, 2017(actual)
- Construction end
- Dec 31, 2019(actual)
Against the original forecast
- Construction start10 months lateforecast Jan 15, 2017
- Construction end3 months earlyforecast Mar 31, 2020
Also in Vaughan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49066 in the federal list. How to read these figures.