Main Street Sewage Treatment Plant Filter Compressor Replacements
Federal contribution
$14,671
Federal share49%
of $30.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 16, 2017
Built
Approved 4 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Penetanguishene
- Construction start
- Aug 31, 2017(actual)
- Construction end
- Dec 21, 2017(actual)
Against the original forecast
- Construction start7 months lateforecast Feb 6, 2017
- Construction end7 months lateforecast May 31, 2017