Design and Construction of the McGee Liftstation Replacement
Federal contribution
$646,905
Federal share35%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Pembroke
- Construction start
- Jan 28, 2017(actual)
- Construction end
- Oct 26, 2018(actual)
Against the original forecast
- Construction start10 months lateforecast Apr 1, 2016
- Construction end3 months lateforecast Jul 31, 2018
Also in Pembroke
- HVAC System UV Treatment; HVAC Duct Sealing; Ventilation$2.2M
- Reconstruction of a Section of Pembroke Street West$2.0M
- Bennet Street and Boundary Road Watermain Replacement and Taylor Bridge Watermain Suspension$1.9M
- HVAC Upgrades; Portable Replacement; Installation of Bottle Filling Stations$1.5M
- Algonquin Trail North Active Transportation Enhancements$1.5M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49106 in the federal list. How to read these figures.