Lakeshore West Pollution Control Plant Main Motor Control Center Panel

Kingsville, Ontario

completeWastewaterCWWF
Federal contribution
$75,000
Federal share50%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 12, 2017
201820192020
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Kingsville
Construction start
May 1, 2017(actual)
Construction end
Jan 28, 2020(actual)

Against the original forecast

  • Construction start4 months earlyforecast Sep 1, 2017
  • Construction end8 weeks lateforecast Dec 6, 2019

Also in Kingsville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49111 in the federal list. How to read these figures.