Upgrade to ditches along Guiney Road to prevent flooding and damage to roadway

Brudenell, Lyndoch and Raglan, Ontario

completeWastewaterCWWF
Federal contribution
$38,500
Federal share50%

of $77.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Aug 21, 2017(actual)
Construction end
Sep 1, 2017(actual)

Against the original forecast

  • Construction start4 months lateforecast May 1, 2017
  • Construction end4 weeks earlyforecast Sep 30, 2017