Replacement of existing culverts to prevent flooding
Brudenell, Lyndoch and Raglan, Ontario
Federal contribution
$11,500
Federal share50%
of $23.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Brudenell, Lyndoch and Raglan, Township of
- Construction start
- Sep 11, 2017(actual)
- Construction end
- Sep 13, 2017(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2017
- Construction end2 weeks earlyforecast Sep 30, 2017
Also in Brudenell, Lyndoch and Raglan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49117 in the federal list. How to read these figures.