Replacement of wastewater pipes and sewage separation
Federal contribution
$285,200
Federal share33%
of $855.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 16, 2018
20182019
Built
Approved 11 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Montréal West
- Construction start
- Jun 28, 2018(actual)
- Construction end
- Dec 31, 2018(actual)
Also in Montréal-Ouest
- Reconstruction of the sports and recreation center$6.3M
- Replacement of MCCs (Main Electrical Distribution) at Lakeshore General Hospital (LGH) - Phase 5$2.1M
- Repair and upgrades to the University Family Medicine Group (GMF-U) department as well as to the H Norma and Robert Hayes buildings of the St. Mary's Hospital Center (SMHC)$1.2M
- Increase in the capacity of the electrical panel at the long term care facility - Centre d'hébergement (CH) de Lachine$960.0K
- Renewal of water pipes$869.1K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49161 in the federal list. How to read these figures.