Brandon - Diesel Exhaust Fluid - Bulk Tank Filling Station
Federal contribution
$47,422
Federal share47%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
2018
Built
Approved 5 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Brandon
- Construction start
- Jan 31, 2018(actual)
- Construction end
- Sep 18, 2018(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Feb 26, 2018
- Construction end3 weeks lateforecast Aug 31, 2018