Brandon - Handi Transit Bus Replacement

Brandon, Manitoba

completePublic TransitPTIF
Federal contribution
$250,000
Federal share50%

of $500.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2018
Built

Approved 5 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Brandon
Construction start
Jul 19, 2017(actual)
Construction end
Sep 30, 2018(actual)

Against the original forecast

  • Construction end4 months lateforecast May 31, 2018

Also in Brandon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49234 in the federal list. How to read these figures.