Portage La Prairie - Handi-Van Purchase

Portage la Prairie, Manitoba

completePublic TransitPTIF
Federal contribution
$49,916
Federal share47%

of $106.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 29, 2017
2018
Built

Approved 5 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Portage La Prairie
Construction start
Jan 29, 2018(actual)
Construction end
Jul 31, 2018(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Aug 31, 2018

Also in Portage la Prairie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49254 in the federal list. How to read these figures.