Selkirk - New Transit Bus

Selkirk, Manitoba

completePublic TransitPTIF
Federal contribution
$188,300
Federal share50%

of $376.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2018
Built

Approved 5 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Selkirk
Construction start
May 9, 2017(actual)
Construction end
May 30, 2018(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Apr 30, 2018

Also in Selkirk

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49260 in the federal list. How to read these figures.