Urban Canopy
Federal contribution
$1.0M
$1,000,000
Federal share40%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 23, 2021
today
2021202320252027
BuiltForecast
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Selkirk
- Construction start
- Sep 20, 2021(actual)
- Construction end
- Dec 31, 2027(forecast)
Against the original forecast
- Construction start6 months lateforecast Apr 1, 2021
Also in Selkirk