Downtown Renewal (#8)
Federal contribution
$866,666
Federal share33%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 9, 2017
2018201920202021
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Selkirk
- Construction start
- Jul 15, 2019(actual)
- Construction end
- Mar 17, 2021(actual)
Against the original forecast
- Construction end6 months lateforecast Sep 30, 2020
Also in Selkirk
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51617 in the federal list. How to read these figures.