Back to projects

Selkirk Forcemain and Lift Station

Selkirk, Manitoba

completeWastewaterSCF
Federal contribution
$739,754
Federal share31%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2019
201920202021
Built

Approved 9 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Selkirk
Construction start
Dec 16, 2019(actual)
Construction end
Oct 31, 2021(actual)

Also in Selkirk