Replacement of 200 mm Cast Iron Watermain which Connects the Residents on 11th Line to the Woodstock Distribution System

Oxford, Ontario

completeDrinking WaterCWWF
Federal contribution
$250,679
Federal share48%

of $517.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
County of Oxford
Construction start
Jan 1, 2017(actual)
Construction end
May 18, 2018(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Dec 1, 2016
  • Construction end7 weeks lateforecast Mar 31, 2018

Also in Oxford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49351 in the federal list. How to read these figures.