Extension of water and sanitary services to the Cedar Heights area
Federal contribution
$1.4M
$1,380,952
Federal share50%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
201720182019
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of North Bay
- Construction start
- Feb 1, 2017(actual)
- Construction end
- Sep 30, 2019(actual)
Against the original forecast
- Construction start9 months earlyforecast Nov 1, 2017
Also in North Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49357 in the federal list. How to read these figures.