Purchase of Heated Garage for Fleet Storage

Elliot Lake, Ontario

completePublic TransitPTIF
Federal contribution
$133,750
Federal share50%

of $267.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 12, 2017
2017
Built

Approved 6 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Elliot Lake
Construction start
Sep 1, 2016(actual)
Construction end
Apr 30, 2017(actual)

Against the original forecast

  • Construction start2 months earlyforecast Oct 31, 2016
  • Construction end5 months lateforecast Nov 30, 2016