Electronic Farebox Upgrade for 7 Chair-A-Vans
Federal contribution
$71,232
Federal share50%
of $142.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
20182019
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Niagara Falls
- Construction start
- Oct 10, 2017(actual)
- Construction end
- Jan 31, 2019(actual)
Against the original forecast
- Construction start8 months lateforecast Feb 20, 2017
- Construction end4 weeks lateforecast Dec 31, 2018
Also in Niagara Falls
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49448 in the federal list. How to read these figures.