Radio Upgrade and Replacement for seven (7) vans for Chair-A-Van
Federal contribution
$6,098
Federal share44%
of $13.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
20172018
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Niagara Falls
- Construction start
- Jan 2, 2017(actual)
- Construction end
- Jan 10, 2018(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Jan 16, 2017
- Construction end4 weeks earlyforecast Feb 6, 2018
Also in Niagara Falls
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49449 in the federal list. How to read these figures.