Bus Way and Shelter Rehabilitation and Platform upgrades at Lundy's Lane and Morrison/Dorchester Transit Hubs
Federal contribution
$224,396
Federal share49%
of $457.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
201820192020
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Niagara Falls
- Construction start
- Oct 2, 2017(actual)
- Construction end
- Dec 31, 2019(actual)
Against the original forecast
- Construction start9 months lateforecast Jan 11, 2017
- Construction end6 months lateforecast Jun 30, 2019