Replacement of 6 (six) Cummins ISL diesel engines that have surpassed life expectancy (500,000 km)
Federal contribution
$116,737
Federal share48%
of $244.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
2018
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Niagara Falls
- Construction start
- Sep 18, 2017(actual)
- Construction end
- Jan 18, 2018(actual)
Against the original forecast
- Construction start8 months lateforecast Jan 23, 2017
- Construction end8 weeks earlyforecast Mar 16, 2018
Also in Niagara Falls
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49454 in the federal list. How to read these figures.