Purchase of Fleet Management Software to support the asset management capacity of the Niagara Falls Transit system
Federal contribution
$28,053
Federal share46%
of $61.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
20182019
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Niagara Falls
- Construction start
- Jul 10, 2017(actual)
- Construction end
- Dec 31, 2018(actual)
Against the original forecast
- Construction start6 months lateforecast Jan 3, 2017