Replacement of Exterior Walkway & Curbing at Transit Terminal

Owen Sound, Ontario

completePublic TransitPTIF
Federal contribution
$30,000
Federal share50%

of $60.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 12, 2017
Built

Approved 6 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Oct 2, 2017(actual)
Construction end
Nov 24, 2017(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2017

Also in Owen Sound

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49464 in the federal list. How to read these figures.