Heating, Ventilation and Air Conditioning (HVAC) - Replacement in Transit Terminal
Federal contribution
$6,033
Federal share20%
of $30.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 12, 2017
Built
Approved 6 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the City of Owen Sound
- Construction start
- Sep 16, 2017(actual)
- Construction end
- Oct 29, 2017(actual)
Against the original forecast
- Construction start5 months lateforecast May 1, 2017
- Construction end4 weeks lateforecast Sep 30, 2017
Also in Owen Sound
- Owen Sound Secondary Sewage Upgrade$15.0M
- Construction of Owen Sound Multi-Purpose Recreation Facility$10.9M
- Reconstruction of the Grey-Bruce Line Road$4.1M
- Marine Emergency Duties Training and Research Centre at the Georgian College Owen Sound Campus$1.7M
- Owen Sound Water Treatment Plant Filtration System Improvements$1.6M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49466 in the federal list. How to read these figures.