General Transit Terminal Repairs (signs)
Federal contribution
$1,503
Federal share30%
of $5.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 12, 2017
ApprovedMar 19, 2018
2018
Built
Approved 10 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the City of Owen Sound
- Construction start
- Dec 1, 2017(actual)
- Construction end
- Mar 19, 2018(actual)
Also in Owen Sound
- Owen Sound Secondary Sewage Upgrade$15.0M
- Construction of Owen Sound Multi-Purpose Recreation Facility$10.9M
- Reconstruction of the Grey-Bruce Line Road$4.1M
- Marine Emergency Duties Training and Research Centre at the Georgian College Owen Sound Campus$1.7M
- Owen Sound Water Treatment Plant Filtration System Improvements$1.6M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49468 in the federal list. How to read these figures.