Active Transportation Improvements

Waterloo, Ontario

completeActive TransportationPTIF
Federal contribution
$2.5M
$2,500,000
Federal share50%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2017
2018201920202021
Built
Program
Public Transit Infrastructure Fund
Construction start
Mar 8, 2017(actual)
Construction end
Jul 31, 2021(actual)

Against the original forecast

  • Construction start4 months lateforecast Nov 1, 2016