Onboard Camera Replacement
Federal contribution
$886,010
Federal share44%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2017
2018
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Regional Municipality of Waterloo
- Construction start
- Apr 12, 2017(actual)
- Construction end
- Mar 31, 2018(actual)
Against the original forecast
- Construction start3 months lateforecast Jan 1, 2017