Onboard Traffic Signal Priority Equipment (285 buses)
Federal contribution
$500,000
Federal share50%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2017
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Regional Municipality of Waterloo
- Construction start
- May 16, 2017(actual)
- Construction end
- Nov 30, 2017(actual)
Against the original forecast
- Construction start4 months lateforecast Jan 1, 2017
- Construction end4 months earlyforecast Mar 31, 2018
Also in Waterloo
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49516 in the federal list. How to read these figures.