Transit Priority Design Studies

Waterloo, Ontario

completePublic TransitPTIF
Federal contribution
$600,000
Federal share50%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2017
201820192020
Built
Program
Public Transit Infrastructure Fund
Construction start
May 16, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start4 months lateforecast Jan 1, 2017