Cast Iron Watermain Replacement On Two Streets in the City of Markham
Federal contribution
$1.2M
$1,198,417
Federal share29%
of $4.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Markham
- Construction start
- May 1, 2017(actual)
- Construction end
- Dec 5, 2018(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 1, 2017
- Construction end13 months earlyforecast Dec 31, 2019
Also in Markham
- City of Markhams Flood Control$48.6M
- Highway 404 - High Occupancy Vehicle Lanes$46.1M
- West Thornhill Flood Control on Three Streets with Structural Sewer Replacement in the City of Markham$4.5M
- Enhancing Health and Safety at City Facilities$4.2M
- Facility Accessibility, Energy Retrofit and Emergency Operations Centre Rehabilitation$2.4M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49521 in the federal list. How to read these figures.