High Street Sanitary Sewer Replacement
Federal contribution
$84,188
Federal share50%
of $168.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 9, 2017
2018
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Souris
- Construction start
- Aug 14, 2017(actual)
- Construction end
- Jul 15, 2018(actual)
Against the original forecast
- Construction end8 months lateforecast Oct 31, 2017
Also in Souris