East Royalty Lift Station

Charlottetown, Prince Edward Island

completeWastewaterCWWF
Federal contribution
$1.9M
$1,925,000
Federal share50%

of $3.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 25, 2017
2018201920202021
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Charlottetown
Construction start
Sep 24, 2018(actual)
Construction end
Dec 31, 2020(actual)

Against the original forecast

  • Construction end9 months lateforecast Mar 31, 2020