Stormwater Enhancement along Dufferin, Main, Prince William and Elder Streets

Alberton, Prince Edward Island

completeWastewaterCWWF
Federal contribution
$64,363
Federal share50%

of $128.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 9, 2017
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Alberton
Construction start
Oct 1, 2017(actual)
Construction end
Nov 7, 2017(actual)

Against the original forecast

  • Construction end8 weeks earlyforecast Dec 31, 2017