Replacement of the Grit Blower at the Pollution Control Plant
Federal contribution
$20,000
Federal share50%
of $40.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 12, 2017
201820192020
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Essex
- Construction start
- Aug 30, 2017(actual)
- Construction end
- Jan 28, 2020(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Oct 1, 2017
- Construction end3 months lateforecast Oct 30, 2019
Also in Essex
- Essex County Road 50 West - Paved Shoulders: Historic Scenic component of the Great Lakes Waterfront Trail$2.3M
- Reconstruction of Dunn Road$1.2M
- Reconstruction of 3rd Concession/Roseborough Road and Hanlan Street$898.8K
- Construction of Harrow Soccer Complex$779.2K
- McGregor Library and Community Centre$578.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49557 in the federal list. How to read these figures.