Fraser Street Stormwater System Upgrade

Montague, Prince Edward Island

completeWastewaterCWWF
Federal contribution
$270,000
Federal share50%

of $540.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 9, 2017
2018
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jul 28, 2018(actual)
Construction end
Sep 4, 2018(actual)

Against the original forecast

  • Construction start11 months lateforecast Aug 15, 2017
  • Construction end7 months earlyforecast Mar 31, 2019

Also in Montague

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49559 in the federal list. How to read these figures.