Georgetown Water System Upgrades

Georgetown, Prince Edward Island

completeWastewaterCWWF
Federal contribution
$75,000
Federal share50%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 9, 2017
20182019
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Nov 1, 2017(actual)
Construction end
Jan 15, 2019(actual)

Against the original forecast

  • Construction start3 months lateforecast Aug 14, 2017
  • Construction end16 months lateforecast Sep 29, 2017