Upgrades to the Colchester South Lagoons and Pump Station including Aerator, Motor Control Center (MCC) Panels and Sewage Pumps

Essex, Ontario

completeWastewaterCWWF
Federal contribution
$237,500
Federal share50%

of $475.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 12, 2017
201820192020
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Essex
Construction start
Aug 30, 2017(actual)
Construction end
Jan 28, 2020(actual)

Against the original forecast

  • Construction start6 months lateforecast Feb 15, 2017
  • Construction end2 months earlyforecast Mar 31, 2020