Back to projects

Bus maintenance management and planning system – Inventory count and determination of asset condition phase

Laval, Quebec

completePublic TransitPTIF
Federal contribution
$128,600
Federal share50%

of $257.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 8, 2017
20182019202020212022
Built

Approved 2 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Dec 1, 2017(actual)
Construction end
Dec 31, 2021(actual)

Also in Laval

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49630 in the federal list. How to read these figures.