Back to projects

Purchase and installation of on-board equipment – Fleet increase for 2016–17 buses phase

Laval, Quebec

completePublic TransitPTIF
Federal contribution
$237,739
Federal share50%

of $475.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 8, 2017
Built

Approved 2 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jan 25, 2017(actual)
Construction end
Mar 29, 2017(actual)

Also in Laval