Purchase of a self-levelling platform and lifts

Laval, Quebec

completePublic TransitPTIF
Federal contribution
$34,693
Federal share50%

of $69.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 8, 2017
2018
Built

Approved 2 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jul 1, 2017(actual)
Construction end
Mar 31, 2018(actual)